Question: Task Description Duration (days) 1 Design facility 20d 2 Site levelling 20d 3 Lay foundation 40d 4 Erect walls 60d 5 Build roof 60d 6
| Task | Description | Duration (days) |
| 1 | Design facility | 20d |
| 2 | Site levelling | 20d |
| 3 | Lay foundation | 40d |
| 4 | Erect walls | 60d |
| 5 | Build roof | 60d |
| 6 | Electrical work | 20d |
| 7 | Plumbing | 20d |
| 8 | Painting | 20d |
| 9 | Internal fittings | 20d |
| 10 | New site fully operational | 0d |
Use the above data to prepare a network diagram ( Use ms-project )
Identify the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
