Question: Task Description Predecessor Task Duration (Days) A Build internal components - 7 B Modify roof and floor - 6 C Construct collection stack A 4
| Task | Description | Predecessor | Task Duration (Days) |
| A | Build internal components | - | 7 |
| B | Modify roof and floor | - | 6 |
| C | Construct collection stack | A | 4 |
| D | Pour concrete and install frame | B | 6 |
| E | Build hi-temp burner | B | 8 |
| F | Install control system | C | 6 |
| G | Install air-pollution control device | C | 4 |
| H | Inspect and test | D,F | 2 |
| I | Obtain financing | G,H | 4 |
Required:
- Develop the network of the project (5marks)
- Determine the critical path and identify any non-critical tasks in the project (2marks)
- Calculate the planned duration of the project (2marks)
- Explain any five Key Areas of Responsibility for an Operations Manager (5marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
