Question: Task Description Predecessor Task Duration (Days) A Build internal components - 7 B Modify roof and floor - 6 C Construct collection stack A 4

Task

Description

Predecessor

Task Duration (Days)

A

Build internal components

-

7

B

Modify roof and floor

-

6

C

Construct collection stack

A

4

D

Pour concrete and install frame

B

6

E

Build hi-temp burner

B

8

F

Install control system

C

6

G

Install air-pollution control device

C

4

H

Inspect and test

D,F

2

I

Obtain financing

G,H

4

Required:

  1. Develop the network of the project (5marks)
  2. Determine the critical path and identify any non-critical tasks in the project (2marks)
  3. Calculate the planned duration of the project (2marks)
  4. Explain any five Key Areas of Responsibility for an Operations Manager (5marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!