Question: Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 3 A 4 B 5 C 3 A D 3 A E 4 B C F 3
| Task | Duration (hours) | Predecessor 1 | Predecessor 2 | Predecessor 3 |
| A | 4 | |||
| B | 5 | |||
| C | 3 | A | ||
| D | 3 | A | ||
| E | 4 | B | C | |
| F | 3 | B | C | |
| G | 5 | D | E | F |
| H | 1 | G |
Draw the appropriate network for this project
What would the cycle time be if the goal is to produce 20 units per month (the plant operates 160 hours per month)?
What is the number of workstations needed?
Balance the process.
What is the efficiency of the balanced process?