Question: Task Duration Predecessor A 5 Start B 6 A C 2 B D 7 A E 3 D F 2 C,E What is slack time
| Task | Duration | Predecessor |
| A | 5 | Start |
| B | 6 | A |
| C | 2 | B |
| D | 7 | A |
| E | 3 | D |
| F | 2 | C,E |
What is slack time for B?