Question: Task ID Float Immediate Precedences Durations (days) A Start 10 B A 15 C A 5 D B 25 E C 31 F D 10

Task ID Float Immediate Precedences Durations

Task ID Float Immediate Precedences Durations (days) A Start 10 B A 15 C A 5 D B 25 E C 31 F D 10 G D 8 H D, E 12 1 E 17 J F, G, H 10 J 5 L 1 7 Finish K, L 0 Using the following WBS, you must elaborate the corresponding PDM Diagram and provide answers for the following questions: 1. Create the corresponding Network Diagram, find the total duration of the project, fill the Float in the corresponding column in the table. 2. How much can activity E be delayed without delaying the whole project? 3. How much can activity I be delayed without delaying the whole project