Question: Your team is handling the project scheduling for Acme Construction. Today you need to analyze some schedule information for a brick house that Acme will
Your team is handling the project scheduling for Acme Construction. Today you need to analyze some schedule information for a brick house that Acme will be building starting the first of next month in Dearborn. All activity relationships are Finish-to-Start. The sequence of activities and time estimates is as follows:
| Activity ID | Description | Predecessor | Estimated Duration (in days) |
| a | Start | 0 | |
| b | Excavate and pour footers | a | 4 |
| c | Pour concrete foundation | b | 2 |
| d | Erect wooden frame including rough roof | c | 4 |
| e | Lay brickwork | d | 6 |
| f | Install basement drains and plumbing | e | 1 |
| g | Pour basement floor | f | 2 |
| h | Install rough plumbing | f | 3 |
| i | Install rough wiring | d | 2 |
| j | Install heating, ventilation and AC | d,g | 4 |
| k | Hang dry wall, mud, tape and finish | i,j,h | 10 |
| l | Lay unfinish hardwood flooring | k | 3 |
| m | Install kitchen fixtures | l | 1 |
| n | Install finish plumbing | l | 2 |
| o | Finish carpentry | l | 3 |
| p | Finish roofing and flashing | o | 2 |
| q | Fasten gutters and downspouts | p | 1 |
| r | Install French drain | c | 1 |
| s | Sand and finish flooring | o,t | 2 |
| t | Paint interior | m,n | 3 |
| u | Finish electrical work | t | 1 |
| v | Finish grading | q,r | 2 |
| w | Pour walks and complete landscaping | v | 5 |
| z | Finish | s,u,w | 0 |
- Create a MS Word document to store your work including your diagram (can be an attachment) and your written answers.
- Draw a network diagram (using the Precedence Diagramming Method as shown below) showing the ES, EF, LS, LF dates assuming the project starts on the first of next month and observes a 5-day work week. Include the activity ID and duration for each activity. You can draw the diagram in PowerPoint or on-paper and take a clear, readable picture with your phone. If using a different drawing package, convert your diagram to a .pdf for attachment to your MS Word document.
- Determine the critical path and mark it (with thicker arrows) on your diagram. What is the number of days in the critical path and the expected finish date?
- If the actual duration of activities a to g is exactly the same as the planned duration but activity h-Rough Plumbing takes 2 days instead of 1 day, how will this impact the expected completion date of the project?
- What is the free float of activity v-Finish Grading? How did you calculate this?
- What is the total float of activity h-Rough Plumbing? How did you calculate this?
- To shorten the project, the chief contractor on the project has suggested assigning more carpenters to activity d. This would reduce the duration of task d from 4 days to 2 days. Will this help or not? How will it change the project schedule?
- Part of the reason that task k takes 10 days is because the drywall mud (also called joint compound) has to dry after it is applied before it can be sanded. The project could switch to a fast drying mud that would reduce the duration of task k by 2 days for a new duration of 8 days. But the fast dry mud will cost a extra $500. Under what conditions would it make business sense to make the switch to fast drying mud?
- What would the finish date be if using a 6-day work week instead of a 5 day work week?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
