Question: Task Immediate Predecessor Optimistic Most Likely Pessimistic A 1 2 3 B A 4 5 6 C B 3 6 15 D B 2 4
| Task | Immediate Predecessor | Optimistic | Most Likely | Pessimistic |
| A |
| 1 | 2 | 3 |
| B | A | 4 | 5 | 6 |
| C | B | 3 | 6 | 15 |
| D | B | 2 | 4 | 6 |
| E | C | 1 | 4 | 7 |
| F | D | 2 | 3 | 4 |
| G | E,F | 4 | 6 | 8 |
Calculate the average time for task C.
What is the critical path?
What is the estimated completion time?