Question: Task: Information for the Project Charter: Let s imagine a construction firm that s going through the initiation phase of a residential construction project, more

Task:
Information for the Project Charter:
Lets imagine a construction firm thats going through the initiation phase of a residential
construction project, more specifically an apartment complex.
Project Information
Company: Acme Construction Co
Project Name: Luxury Apartments at York
Project Description: The project consists of the construction of a luxury apartment
complex, featuring three types of floor plans going from 800 to 1,350 square feet
Roles & Responsibilities
Lead Architect: Helena Johnson
Lead Engineer: Samuel Weiss
Construction Project Manager: Frederick Terry
Cost Estimator: Danielle DuPont
Project Administrator: Luke Robinson
Site Supervisor: David Rosenthal
Project Vision and Objectives
Project Vision: Completion on time, within budget, to exploit housing needs in the area.
Project Objectives:
1. Hire construction crew members as needed,
2. Procure any materials or equipment as needed,
3. Transport materials and equipment to the construction site as instructed by the
construction project manager and site supervisor,
4. Fill out daily construction reports to monitor the performance of the construction team.
Business Case
The district is ripe for housing. Recent mixed-use construction has produced popular retail
and restaurants. The area is lacking in luxury residential housing for the moneyed class
which has increasingly made this part of the city a destination. Attached is supporting
research, demographics, etc.
Project Scope
The construction project will be built as per the construction drawings, specifications and
other documents such as the construction plan and construction schedule.
Project Timeline
The project is expected to start by the last quarter of the year and be completed between 12-
16 months.
Hint: Use the table to distribute the timeline in a reasonable way.
Project Budget
The project budget is $15 million, based on the number of units and their square footage, as
specified in the construction drawings, architectural designs and computer-assisted
designs (CAD) models. The project budgeting process was completed thanks to a cross-
functional effort by the architecture, engineering and cost estimation team.
Hint: Use the table to distribute the timeline in a reasonable way.
Project Assumptions
Its assumed that no act of God such as earthquakes, tornados or hurricanes will
cause the project to stop.
Its assumed that the equipment will be in optimal condition so that the construction
phase will be completed normally.
Its assumed that there are enough construction crew employees to complete the
project.
Its assumed that construction subcontractors will complete their work on time.
Project Constraints
The project shall not take longer than 18 months. If the construction team is running
behind schedule, additional subcontractors might be hired without exceeding the
project budget.
The project has a budget of $15 million that must be monitored by the construction
project manager. This project budget already contemplates a contingency fund in
case there are over-costs, so it should not be exceeded for any reason.
Project Risks
The following risks might affect this project:
Unexpected increases in material costs
Unavailability of project resources such as labor, materials and equipment due to
external factors
Damage or theft of company equipment
Natural disasters
Project Requirements and Success Criteria
The quality, safety standards, success criteria and other requirements for this project are
explained in the construction drawings and construction specification documents. These
include but are not limited to the quality of materials, skills required from the construction
crew, environmental compliance standards and building codes.
Fill IN BELOW based on the above scenario.
PROBLEM Or ISSUE -
PURPOSE OF PROJECT -
BUSINESS CASE -
GOALS / METRICS -
EXPECTED DELIVERABLE -
PROJECT SCOPE WITHIN SCOPE -
OUTSIDE SCOPE
TENTATIVE SCHEDULE
KEY MILESTONE START FINISH Start Finish
Form Project Team / Preliminary Review / Scope
Finalize Project Plan / Charter / Kick Off
Define Phase
Measurement Phase
Analysis Phase
Improvement Phase
Control Phase
Project Summary Report and Close Out
RESOURCES
PROJECT TEAM -
SUPPORT RESOURCE -
SPECIAL NEEDS -
COSTS
COST TYPE VENDOR / LABOR NAMES RATE QTY AMOUNT
TOTAL COSTS $
BENEFITS AND CUSTOMERS
PROCESS OWNER -
KEY STAKEHOLDERS -
FINAL CUSTOMER -
EXPECTED BENEFITS -
TYPE OF BENEFIT BASIS OF ESTIMATE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!