Question: Task Information for the Time-Cost Model Exercise Normal Crash Immediate Normal Crash Time Time Predecessors Cost Cost (days) (days) NONE 2 $5,000 $11,000 'A $10,000

Task Information for the Time-Cost Model Exercise
Task Information for the Time-Cost Model Exercise Normal Crash Immediate Normal Crash Time Time Predecessors Cost Cost (days) (days) NONE 2 $5,000 $11,000 'A $10,000 $20,000 $6,000 $9,000 $4,000 $8,000 $8,000 Cost per week to expedite $6,000 $5,000 $3,000 $4,000! | $0 5 Band C When completing the network diagram and assessing if any activities have slack, which project activity has 1 day of slack? O A o OD

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts