Question: Task Label Task Description Estimated Duration ( days ) Immediate Predecessors A Pilot system 1 7 None B Gather sales data 2 1 A C

Task Label Task Description Estimated Duration (days) Immediate Predecessors
A Pilot system 17 None
B Gather sales data 21 A
C Identify software 6 B
D Validate data 11 B
E Input RootVendor data 5 C, D
F Train vendors 7 E Using this table, create a critical path for each task. Each task needs an ES, EF, LS, LF, and Slack