Question: Task List with PERT Estimates: Task Dependencies: Questions: PERT Analysis: Calculate the expected time ( T e x p e c t e d )
Task List with PERT Estimates:
Task Dependencies:
Questions:
PERT Analysis:
Calculate the expected time for each task using PERT.
Critical Path in CPM: using the Expected time as the duration for each activity
Construct a network diagram
Complete the backward and forward pass
Calculate slackfloat
Identify the critical path
Total Project Duration:
Determine the total duration for completing the campus event project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
