Question: 1. During planning for the implementation of a software project, the Work Breakdown Structure consisted of ten tasks and their dependencies as summarized in Table

1. During planning for the implementation of a software project, the Work Breakdown Structure consisted of ten tasks and their dependencies as summarized in Table 1. Draw a Network Diagram to represent these tasks and their dependencies. Using forward analysis, identify and clearly indicate on your diagram, the critical path and earliest completion time of the software project. Using backward analysis, calculate the Slack Time values for tasks C and F. . Task A B D E F G H I J Table 1 Expected Task Dependencies (Tasks which must be duration (days) completed before a task can commence.) 3 5 A 2. B 3 B 6 C,D 7 D 5 E 3 G 2 G 3 F T| QQ TO