Question: Task Minimum Expected Maximum Predecessor A 1 2 4 - B 2 3 7 - C 4 5 8 - D 6 6 7 A,B

Task Minimum Expected Maximum Predecessor A 1 2 4 - B 2 3 7 - C 4 5 8 - D 6 6 7 A,B E 6 8 11 B,C F 3 5 8 D G 3 5 6 E H 1 5 5 F I 2 6 7 F,G J 1 2 3 G The expected project completion time