Question: Task Name Category Start Date Planned Duration (days) Actual Duration (days) Risk Level Buffer Zone (days) Planned End Date Actual End Date Conduct Market Research
| Task Name | Category | Start Date | Planned Duration (days) | Actual Duration (days) | Risk Level | Buffer Zone (days) | Planned End Date | Actual End Date |
| Conduct Market Research & API Selection | Planning and Initial Research | 9/8/2024 | 3 | 4 | Medium | 1 | 12/8/2024 | 13/8/2024 |
| Decide on Software and Tools | Planning and Initial Research | 9/8/2024 | 3 | 3 | Low | 0 | 12/8/2024 | 13/8/2024 |
| Begin Backend Development | Backend Development | 12/8/2024 | 5 | 6 | Medium | 1 | 17/8/2024 | 18/8/2024 |
| Setting up a NodeJS ExpressJs server with TypeScript | Backend Development | 17/8/2024 | 5 | 6 | Medium | 1 | 22/8/2024 | 23/8/2024 |
| Develop and test the routes, controllers, and services for the locations | Backend Development | 22/8/2024 | 5 | 6 | High | 1 | 27/8/2024 | 28/8/2024 |
| Complete Backend Development | Backend Development | 27/8/2024 | 4 | 5 | High | 1 | 31/8/2024 | 1/9/2024 |
| Develop and test the routes, controllers, and services for the trips | Backend Development | 1/9/2024 | 4 | 4 | High | 0 | 5/9/2024 | 5/9/2024 |
| Develop the socket connection for editing the contents of a trip | Backend Development | 1/9/2024 | 4 | 4 | High | 0 | 5/9/2024 | 5/9/2024 |
| Begin Frontend Development | Frontend Development | 16/8/2024 | 4 | 6 | Medium | 2 | 20/8/2024 | 22/8/2024 |
| Create user profile page with ability for creating and deleting trips | Frontend Development | 21/8/2024 | 5 | 6 | High | 1 | 26/8/2024 | 27/9/2024 |
| Implement search and pagination in locations page | Frontend Development | 26/8/2024 | 4 | 4 | Medium | 0 | 30/8/2024 | 30/8/2024 |
| API Integration in Frontend | Frontend Development | 30/8/2024 | 4 | 5 | Medium | 1 | 3/9/2024 | 4/9/2024 |
| Code the socket connection to the backend | Frontend Development | 30/8/2024 | 3 | 4 | High | 1 | 2/9/2024 | 3/9/2024 |
| Coded ability to add and remove collaborators to a trip | Frontend Development | 1/9/2024 | 2 | 3 | High | 1 | 3/9/2024 | 4/9/2024 |
| Review Background & Market Research | Review and Iteration | 24/8/2024 | 2 | 2 | Low | 0 | 26/8/2024 | 27/8/2024 |
| Review and Refine Concepts | Review and Iteration | 28/8/2024 | 2 | 2 | Medium | 0 | 30/8/2024 | 31/8/2024 |
| Iterate Based on Feedback | Review and Iteration | 31/8/2024 | 3 | 3 | Medium | 0 | 3/9/2024 | 5/9/2024 |
| Start System Development Section | System Development and Prototyping | 3/9/2024 | 3 | 3 | Medium | 0 | 6/9/2024 | 6/9/2024 |
| Start Working on Prototype Section | System Development and Prototyping | 6/9/2024 | 1 | 2 | Medium | 0 | 7/9/2024 | 8/9/2024 |
| Review Prototype Section | System Development and Prototyping | 7/9/2024 | 1 | 1 | Medium | 0 | 9/9/2024 | 9/9/2024 |
| Start Analysis and Evaluation Section | Finalization | 2/9/2024 | 3 | 4 | High | 1 | 5/9/2024 | 6/9/2024 |
| Start Conclusion and Finalise Report | Finalization | 6/9/2024 | 2 | 2 | Low | 0 | 8/9/2024 | 8/9/2024 |
| Check Code Quality & Record Video | Finalization | 8/9/2024 | 2 | 2 | Medium | 0 | 9/9/2024 | 9/9/2024 |
| Conduct Final Check & Submission | Finalization | 8/9/2024 | 2 | 2 | High | 0 | 9/9/2024 | 9/9/2024 |
please help me making a gantt chart for my progress above? Ive been trying and got nowhere:') Here below is an example how it should look like, Please Please don't let it be chatgpt generated ones.

Name + 1. Project lgeation Brainstorm Possible Ideas Actual Duration: Brainstorm Possible Ideas Pitch Individual Idea and Select the Best Idea Actual Duration: Pitch Individual Idea and Se w 2. Concept Development Define a Clear Concept with Aims and Goals Actual Duration: Define a Clear Concept with Find the Need for the Proposed Concept fro. Actual Duration: Find the Need for the Propo * 3. User Requirements Gathering Identify and document user needs, preferenc Buffer Zone: Identify and document user nee Actual Duration: Identify and document user Analyze gathered requirements to prioritize Actual Duration: Analyze gathered requirem + 4 Market Research Market Research Analysis Buffer Zone: Market Research Analysis Actual Duration: Market Research Analysis Conduct SWOT and PESTLE Analysis Actual Duration: Conduct SWOT and PESTL 5. Prototype Development Design Low-Fidelity Prototype (First Iteration) Actual Duration: Design Low-Fidelity Prototy User Testing Feedback For Low-Fidelity Pro Actual Duration: User Testing Feedback For Design Second Iteration of Low Fidelity Prot Actual Duration: Design Second lteration of Design High-Fidelity Prototype Actual Duration: Design High-Fidelity Prototy = 6.Technical Specifications Technical & Functional Specifications Actual Duration: Technical & Functional Spe Provide a Clear Performance Analysis Actual Duration: Provide a Clear Performanc + 7.Coding Phase Backend Development Actual Progress: Backend Development = 8 Report Finalisation Edit and Finalise the Report Actual Duration: Edit and Finalise the Report Final Report Review and Submit Actual Duration: Final Report Review and Su May, 2024 09 ... 12 May > 19 May 26 May Jun, 2024 Jul, 2024 02 Jun 08 Jun 16 Jun 23 Jun 30 Jun A Iil altl Powered by: onlinegantt.com 1'1 07 Jul 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts