Question: Task Name Optimistic Likely Pessimistic Expected Duration Variance A 0.8 2 3 1.97 0.13 B 9 20 40 21.50 26.69 C 9 15 20 14.83
| Task Name | Optimistic | Likely | Pessimistic | Expected Duration | Variance |
| A | 0.8 | 2 | 3 | 1.97 | 0.13 |
| B | 9 | 20 | 40 | 21.50 | 26.69 |
| C | 9 | 15 | 20 | 14.83 | 3.36 |
| D | 1 | 1 | 2 | 1.17 | 0.03 |
| E | 0 | 1 | 1 | 0.83 | 0.03 |
| F | 4 | 5 | 7 | 5.17 | 0.25 |
| G | 5 | 7 | 8 | 6.83 | 0.25 |
| H | 8 | 11 | 15 | 11.17 | 1.36 |
| I | 1 | 1 | 2 | 1.17 | 0.03 |
| J | 0.8 | 1 | 2 | 1.13 | 0.0 |
| K | 0.7 | 1 | 1 | 0.95 | 0.00 |
| L | 1.5 | 2 | 2.5 | 2.00 | 0.03 |
| M | 0.4 | 0.5 | 1 | 0.57 | 0.01 |
| N | 0.1 | 0.1 | 0.1 | 0.10 | 0.00 |
| O | 0.5 | 0.5 | 1 | 0.58 | 0.01 |
| P | 0.1 | 0.1 | 0.1 | 0.10 | 0.00 |
| Q | 1 | 1 | 2 | 1.17 | 0.03 |
| R | 0.5 | 0.5 | 1 | 0.58 | 0.01 |
| S | 0.2 | 0.5 | 0.5 | 0.45 | 0.00 |
A-B-D-E-F-G-H-I-L-M-P-Q-R-S is the critical path
State all the ES, EF, LS, LF, and Slack Times for each activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock