Question: Task Name Start Date Planned Duration (days) Actual Duration (days) Risk Level Buffer Zone (days) Planned End Date Actual End Date Conduct Market Research &
| Task Name | Start Date | Planned Duration (days) | Actual Duration (days) | Risk Level | Buffer Zone (days) | Planned End Date | Actual End Date |
|---|---|---|---|---|---|---|---|
| Conduct Market Research & API Selection | 2024-07-09 | 7 | 8 | Medium | 1 | 2024-07-16 | 2024-07-17 |
| Decide on Software and Tools | 2024-07-09 | 7 | 7 | Low | 0 | 2024-07-16 | 2024-07-16 |
| Begin Backend Development | 2024-07-17 | 14 | 15 | Medium | 2 | 2024-07-31 | 2024-08-01 |
| Setting up a NodeJS ExpressJs server with TypeScript | 2024-07-31 | 10 | 12 | Medium | 1 | 2024-08-10 | 2024-08-12 |
| Develop and test the routes, controllers, and services for the locations | 2024-08-10 | 7 | 8 | High | 2 | 2024-08-17 | 2024-08-18 |
| Complete Backend Development | 2024-08-18 | 7 | 8 | High | 1 | 2024-08-25 | 2024-08-26 |
| Develop and test the routes, controllers, and services for the trips | 2024-08-26 | 7 | 8 | High | 1 | 2024-09-02 | 2024-09-03 |
| Develop the socket connection for editing the contents of a trip | 2024-08-26 | 7 | 8 | High | 1 | 2024-09-02 | 2024-09-03 |
| Begin Frontend Development | 2024-07-24 | 10 | 12 | Medium | 1 | 2024-08-03 | 2024-08-05 |
| Creating user profile page with ability for creating and deleting trips | 2024-08-05 | 7 | 8 | High | 2 | 2024-08-12 | 2024-08-13 |
| Implement search and pagination in locations page | 2024-08-13 | 7 | 7 | Medium | 0 | 2024-08-20 | 2024-08-20 |
| API Integration in Frontend | 2024-08-20 | 7 | 8 | Medium | 1 | 2024-08-27 | 2024-08-28 |
| Code the socket connection to the backend | 2024-08-20 | 5 | 6 | High | 1 | 2024-08-25 | 2024-08-26 |
| Coded ability to add and remove collaborators to a trip | 2024-08-26 | 5 | 6 | High | 1 | 2024-08-31 | 2024-09-01 |
| Review Background & Market Research | 2024-07-16 | 7 | 7 | Low | 0 | 2024-07-23 | 2024-07-23 |
| Review and Refine Concepts | 2024-07-23 | 7 | 7 | Medium | 1 | 2024-07-30 | 2024-07-31 |
| Iterate Based on Feedback | 2024-07-31 | 7 | 7 | Medium | 1 | 2024-08-07 | 2024-08-08 |
| Start System Development Section | 2024-08-08 | 7 | 7 | Medium | 1 | 2024-08-15 | 2024-08-16 |
| Start Working on Prototype Section | 2024-08-16 | 5 | 6 | Medium | 1 | 2024-08-21 | 2024-08-22 |
| Review Prototype Section | 2024-08-22 | 5 | 6 | Medium | 1 | 2024-08-27 | 2024-08-28 |
| Start Analysis and Evaluation Section | 2024-08-28 | 7 | 7 | High | 1 | 2024-09-04 | 2024-09-04 |
| Start Conclusion and Finalise Report | 2024-09-04 | 5 | 5 | Low | 0 | 2024-09-09 | 2024-09-09 |
| Check Code Quality & Record Video | 2024-09-04 | 5 | 5 | Medium | 0 | 2024-09-09 | 2024-09-09 |
| Conduct Final Check & Submission | 2024-09-04 | 5 | 5 | High | 0 | 2024-09-09 | 2024-09-09 |
Please help me make a gantt chart for the data above. I ve tried everything and i still can't do it. Please use these below charts as inspiration thank you.


Name + 1. Project lgeation Brainstorm Possible Ideas Actual Duration: Brainstorm Possible Ideas Pitch Individual Idea and Select the Best Idea Actual Duration: Pitch Individual Idea and Se w 2. Concept Development Define a Clear Concept with Aims and Goals Actual Duration: Define a Clear Concept with Find the Need for the Proposed Concept fro. Actual Duration: Find the Need for the Propo * 3. User Requirements Gathering Identify and document user needs, preferenc Buffer Zone: Identify and document user nee Actual Duration: Identify and document user Analyze gathered requirements to prioritize Actual Duration: Analyze gathered requirem + 4 Market Research Market Research Analysis Buffer Zone: Market Research Analysis Actual Duration: Market Research Analysis Conduct SWOT and PESTLE Analysis Actual Duration: Conduct SWOT and PESTL 5. Prototype Development Design Low-Fidelity Prototype (First Iteration) Actual Duration: Design Low-Fidelity Prototy User Testing Feedback For Low-Fidelity Pro Actual Duration: User Testing Feedback For Design Second Iteration of Low Fidelity Prot Actual Duration: Design Second lteration of Design High-Fidelity Prototype Actual Duration: Design High-Fidelity Prototy = 6.Technical Specifications Technical & Functional Specifications Actual Duration: Technical & Functional Spe Provide a Clear Performance Analysis Actual Duration: Provide a Clear Performanc + 7.Coding Phase Backend Development Actual Progress: Backend Development = 8 Report Finalisation Edit and Finalise the Report Actual Duration: Edit and Finalise the Report Final Report Review and Submit Actual Duration: Final Report Review and Su May, 2024 09 ... 12 May > 19 May 26 May Jun, 2024 Jul, 2024 02 Jun 08 Jun 16 Jun 23 Jun 30 Jun A Iil altl Powered by: onlinegantt.com 1'1 07 Jul 1. Gantt Chart Legend: Low Risks Medium Risks High Risks Actual Progress of Project Phases Buffer Zones To-do tasks To-do tasks To-do tasks the completed tasks