Question: Task No Description Duration (Days) Predecessor Tasks 1 Requirement Analysis 15 - 2 Design 30 1 3 Budgeting 35 2 4 Select car with specification
| Task No | Description | Duration (Days) | Predecessor Tasks |
| 1 | Requirement Analysis | 15 | - |
| 2 | Design | 30 | 1 |
| 3 | Budgeting | 35 | 2 |
| 4 | Select car with specification | 40 | 3 |
| 5 | Find dealership | 45 | 4 |
| 6 | Test drive | 50 | 5 |
| 7 | Look for loan if applicable | 55 | 6 |
| 8 | Pay first installment | 60 | 7 |
| 9 | Get car insured and registered | 65 | 8 |
| 10 | finish | 70 | 9 |
- draw Gantt chart from above information