Question: Task No Description Duration (Days) Predecessor Tasks 1 Requirement Analysis 15 - 2 Design 30 1 3 Budgeting 35 2 4 Select car with specification

Task No

Description

Duration (Days)

Predecessor Tasks

1

Requirement Analysis

15

-

2

Design

30

1

3

Budgeting

35

2

4

Select car with specification

40

3

5

Find dealership

45

4

6

Test drive

50

5

7

Look for loan if applicable

55

6

8

Pay first installment

60

7

9

Get car insured and registered

65

8

10

finish

70

9

  1. draw Gantt chart from above information