Question: Task No . Reference WBS Task Brief Label Task Full Description Duration ( D ) Earliest Start ( ES ) Earliest Finish ( EF
Task No "Reference WBS Task Brief Label Task Full Description Duration D Earliest Start ES Earliest Finish EF Task Starts After
Start
Analyse historical sales data Analyse historical sales data to calculated revenue by product mix for each Sales region
Estimate Revenue by Region Run CRM report to obtain target revenue for each Sales region
Average Discount by Product Run CRM report to obtain historical average discount by product
Validate Revenue by Region Contact Regional Sales GMs to validate CRM figures After Task
Calculate Total Revenue by Product Multiply Validated Regional Sales figures by historical by Region then sumup to get Total Revenue by Product After Task and Task
List Price by Product Obtain List Price by Product from Finance
Customer Price by Product Customer Price by Product After Task and Task
Calculate Annual Units by Product Calculate Annual Units by Product Revenue by Product Customer Price by Product After Task and Task
BoM By Product Download Bill of Material By Product from ERP system
Unadjusted Phasein percent Obtain Phasein percent converts annual to weekly demand from Finance
Holiday & Shutdown schedule Obtain Holiday & Shutdown schedule from Operations
Adjusted Phasein percent Remove holidays and shutdown dates from Phasein percent converts annual to weekly demand After Task and Task
Annual demand for parts Calculate Annual demand for parts Annual Units by Product X BoM by Product After Task and Task
Weekly demand for parts Calculate Weekly demand for parts based on Annual demand and Adjusted Phasein percent After Task and Task
Create a
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock