Question: Task Normal time (days) Crash time (days) Normal Cost ($) Crash Cost ($) Predecessor(s) a 20 12 50 70 b 14 12 60 80 c
Task | Normal time (days) | Crash time (days) | Normal Cost ($) | Crash Cost ($) | Predecessor(s) |
a | 20 | 12 | 50 | 70 |
|
b | 14 | 12 | 60 | 80 |
|
c | 7 | 6 | 70 | 160 | b |
d | 2 | 1 | 20 | 50 | a, c |
e | 3 | 2 | 200 | 300 | a, c |
f | 8 | 5 | 100 | 200 | b |
g | 5 | 4 | 50 | 100 | d |
h | 6 | 3 | 60 | 180 | e, f |
1.Draw a AON network diagram for the project. (5 pts)
2.Mark the critical path and state its length using normal time. (5 pts)
3.Calculate crash cost per period for all project activities. (5 pts)
4,The project has to be completed 1 day earlier. Which task should be crashed first? Explain why.
(5 pts)
5.Crash the project by 2 days with the least cost. Which activities have to be crashed? How much is additional cost for this crash? (5 pts)
Step by Step Solution
3.54 Rating (151 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
60d5e1d22850c_227924.pdf
180 KBs PDF File
60d5e1d22850c_227924.docx
120 KBs Word File