Question: Task Number Depends On Task Name Duration Choose clothes Get Dressed Eat breakfast Leave Make coffee Make toast Pour juice Shower Wake up 6.5 6

Task Number Depends On Task Name Duration Choose clothes Get Dressed Eat breakfast Leave Make coffee Make toast Pour juice Shower Wake up 6.5 6 1,8 5, 6, 7 2, 3 3 4 4.5 6 0.5 8.5 0 8 Task Scheduling and Critical Path. Consider the above problem description 1. 2. Draw an event-node graph to represent the above problem Find the earliest completion time, latest completion time and slack time for each task. Assume that the latest completion time for the last task is itsearliest completion time Show all critical tasks and one critical path if there is any 3