Question: Task Predecessor Time (seconds) A none 45 B none 30 C A,B 45 D B 20 E C 10 F D, E 24 G E
| Task | Predecessor | Time (seconds) |
| A | none | 45 |
| B | none | 30 |
| C | A,B | 45 |
| D | B | 20 |
| E | C | 10 |
| F | D, E | 24 |
| G | E | 40 |
If my desired output rate is 75 units per hour, what is the efficiency. of my setup?