Question: 1f. Using the longest task time rule to assign processes to stations, what is the balance delay of the layout? BE PREPARED TO DRAW THE

1f. Using the longest task time rule to assign
1f. Using the longest task time rule to assign processes to stations, what is the balance delay of the layout? BE PREPARED TO DRAW THE DIAGRAM IN CLASS. 3. The following table provides tasks on an assembly line, along with their predecessors and task times, the desired output is 75 units per hour. Immediate Task Predecessor Time (seconds) A None 45 B None 30 AB 48 D B 20 E 10 F D, E 20 G E 40