Question: Task Statement ( Bullet List ) E - mail the managers about the training sessions ( 1 day ) . Then start three tasks: Develop

Task Statement (Bullet List)
E-mail the managers about the training sessions (1 day).
Then start three tasks: Develop the training material (5 days), confirm the training facility arrangements, (2 days), and print the handout material (3 days).
When the training facility is confirmed and handout material is ready, you can hold practice training sessions (2 days).
Finally, when the practice sessions are done and the training material is ready, conduct the training sessions (3 days).
Task A. Identify all predecessor tasks, based on the above bulleted items. Draw a Simple Task Pattern (PERT/CPM Chart - Only on the Tasks #) on the above statements: Use a box for each task and connect the boxes to show dependent, multiple successor, and multiple predecessor patterns.
Task B. Use Microsoft Project, and add the Task Name, Duration and Predecessor tasks to a Gantt Chart from the statements above and your Predecessors. Your Task B should look similar to Figure 3-9 below.
Please use Microsoft Project (or any other Project Management Tool) and do a Gantt Chart. Please add The Task Name, Duration and Predecessors. Once you complete the Gantt Chart, please save it as PDF or you can take a Snap Shot and paste it to your Document that you used for Task A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!