Question: Task Task Length Predecessors A 6 - What is the critical path ? B 8 - C 4 - D 6 A,B E 8 B,C
Task Task Length Predecessors A 6 - What is the critical path ? B 8 - C 4 - D 6 A,B E 8 B,C F 5 D G 6 E H 3 F I 5 F,G J 7 G