Question: Task Task Time (seconds) A 50 B 20 C 40 D 45 E 25 D F 20 B G 10 C, E, F The above

Task Task Time (seconds) A 50 B 20 C 40 D 45 E 25

Task Task Time (seconds) A 50 B 20 C 40 D 45 E 25 D F 20 B G 10 C, E, F The above tasks must be performed on an assembly line in the sequence and times specified. The workstation cycle time is 72 seconds. Using the longest task time to balance the assembly line, the first workstation includes (For each blank write tasks in alphabetical order without space or the second workstation includes , and the third workstation includes comma. For example, if workstation 1 includes task A, task C and task E, write them as ACE, not A,C,E, ACE or CAE.) Tasks that must Precede A -- B