Question: Task Task Time (seconds) Preceding Tasks A 35 - B 5 A C 10 B D 35 B E 10 C,D F 15 E a.
Task Task Time (seconds) Preceding Tasks A 35 - B 5 A C 10 B D 35 B E 10 C,D F 15 E
a. What takt time is required to achieve an hourly output of 90 units per hour?
The takt time required to achieve the production volume of 90 per hour is: :enter your response here seconds per unit. (Enter your response as a whole number.)
b. The minimum number of workstations is: :enter your response here. (Enter your response rounded up to the next whole number.)
c. Use the longest operating time heuristic to assign tasks to workstations. Fill in the table below (enter your responses as whole numbers). (Hint: Number workstations sequentially (starting with 1) in terms of precedence relationships and combine any applicable tasks.)
| Eligible Tasks | Chosen Task | Workstation | Task Time | Slack Time |
| A | A | enter your response here | enter your response here | enter your response here |
| B | B | enter your response here | enter your response here | enter your response here |
| C,F C,D C,E D,E E,F | D F C E |
| F C,E C | C D F E |
| E | E |
| F | F |
d. The efficiency of the line is: :enter your response here. (Enter your response rounded to two decimal places.)
e. The balance delay of the line is enter your response here. (Enter your response rounded to two decimal places.)