Question: Task Task Time (seconds) Tasks that must Precede A 30 -- B 16 A C 19 A D 20 -- E 20 B,C F 18
| Task | Task Time (seconds) | Tasks that must Precede |
| A | 30 | -- |
| B | 16 | A |
| C | 19 | A |
| D | 20 | -- |
| E | 20 | B,C |
| F | 18 | D |
| G | 12 | E |
| H | 45 | F,G |
The above tasks must be performed on an assembly line in the sequence and times specified. The workstation cycle time is 51 seconds. Using the longest task time to balance the assembly line, the first workstation include _______________, the second workstation include _______________, the third workstation include _______________, and the fourth workstation include _______________. (For each blank write tasks in alphabetical order without space or comma. For example, if workstation 1 includes task A, task C and task E, write them as ACE, not A,C,E, A C E or CAE.)