Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: table [ [ Activity ,

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
\table[[Activity,\table[[Time],[(in hours)]],Immediate Predecessor(s)],[A,5.0,-],[B,7.5,-],[C,6.0,A],[D,6.0,B, C],[E,5.0,B, C],[F,7.5,D],[G,4.0,E, F]]
 Task time estimates for the modification of an assembly line at