Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: table [ [ Activity ,

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
\table[[Activity,\table[[Time],[(in hours)]],\table[[Immediate],[Predecessor(s)]]],[A,6.0,-],[B,7.2,-],[C,6.0,A],[D,8.0,B, C],[E,5.1,B, C],[F,7.7,D],[G,5.0,E, F]]
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in