Question: Task time estimates for the modification of an assembly line at Robert Klassen's Ontario factory are as follows. Activity Time (in hours) Immediate Predecessor(s) A
Task time estimates for the modification of an assembly line at Robert Klassen's Ontario factory are as follows.
| Activity | Time (in hours) | Immediate Predecessor(s) |
|
|---|---|---|---|
| A | 6.0 | - | |
| B | 7.5 | - | |
| C | 5.0 | A | |
| D | 6.0 | B, C | |
| E | 4.0 | B, C | |
| F | 7.0 | D | |
| G | 3.0 | E, F |
This exercise contains only parts d, b, and c.
Part 2
d) Use the multipoint curve drawing tool five times, draw a Gantt chart
LOADING...
for activities C through G of the project based on the early times.
Carefully follow the instructions above, and only draw the required objects.
...
Question content area right
Part 1
0246810121416182022242628GFEDCBA0