Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Immediate Predecessor(s) B Activity A B

Task time estimates for the modification of an

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Immediate Predecessor(s) B Activity A B Time (in hours) 5.0 7.5 6.0 7.0 5.1 8.4 4.0 D A B, C B, C E F G Figure 2 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in B Figure 3 F Click to select your answer(s)