Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Immediate Predecessor(s) Figure 1 Activity .

Task time estimates for the modification of an

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Immediate Predecessor(s) Figure 1 Activity . B Time (in hours) 6.0 7.2 6.0 6.0 4.5 8.1 5.0 D E F B, C B, C D E, F G B This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 3 Figure 2 A B Figure 3 B Click to select your answer(s)