Question: Task Time Predecessor 1 0.2 - 2 0.4 1 3 0.1 1 4 0.4 2,3 5 0.1 2 6 0.3 3,4 7 0.2 5 8
|
|
|
|
| Task | Time | Predecessor |
| 1 | 0.2 | - |
| 2 | 0.4 | 1 |
| 3 | 0.1 | 1 |
| 4 | 0.4 | 2,3 |
| 5 | 0.1 | 2 |
| 6 | 0.3 | 3,4 |
| 7 | 0.2 | 5 |
| 8 | 0.2 | 5,6 |
| 9 | 0.4 | 7,8 |
Consider the operations given in Table 1. 47 feet of the oor space along the conveyor is available for installing assembly stations around a closed loop conveyor system. Eeach station is made 6 feet long in order for the operators to work comfortably, and at least 1 feet clearance between stations (except between input and output stations).
- Find the maximum number of stations on conveyor when the target production rate is 90 units per hr.
- Find the maximum number of stations on conveyor when the target production rate is 120 units per hr.
- Find the speed of conveyor when target production rate is 90 units per hr.
- Find the speed of conveyor when target production rate is 120 units per hr.
- Find the task to workstation assignments with Largest Candidate Rule when the target production rate is 90 units per hr.
- Find the total space occupied by the workstations and clearances when the target production rate is 90 units per hr.
- Find the task to workstation assignments with Largest Candidate Rule when the target production rate is 120 units per hr. Adjust the station-sizes using the method we covered in the class.
- Find the allocated space occupied to each workstation, and total space occupied including clearances when the target production rate is 120 units per hr.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts