Question: Task X is expected to take three days to complete. The maximum ( latest ) earliest finish date for any predecessors to task X is

Task X is expected to take three days to complete. The maximum (latest) earliest finish date for any predecessors to task X is 10. Therefore, the earliest finish for task X is: