Question: Task-4 [03] [6 Marks You are working on a 8 months project. You have divided the time into activities and then assigned time frame for
Task-4 [03] [6 Marks You are working on a 8 months project. You have divided the time into activities and then assigned time frame for each activity. Create a "Gantt Chart" showing the following tasks and time period. [05] [5 Marks ACTIVITY MONTH Literature Review 1-4 Data Collection 3-6 Data Analysis 5-7 Documentation 7-8 Presentation 8