Question: Task-4 [03] [6 Marks] You are working on a 8 months project. You have divided the time into activities and then assigned time frame for
![Task-4 [03] [6 Marks] You are working on a 8 months](https://s3.amazonaws.com/si.experts.images/answers/2024/07/66869de968592_28066869de90141d.jpg)
Task-4 [03] [6 Marks] You are working on a 8 months project. You have divided the time into activities and then assigned time frame for each activity. Create a "Gantt Chart" showing the following tasks and time period. [05] [5 Marks) ACTIVITY MONTH Literature Review 1-4 Data Collection 3-6 Data Analysis 5-7 Documentation 7-8 Presentation CO