Zelda Construction enters into a contract with a customer to build a warehouse for $850,000 on March 30, 20155 with a performance bonus of $50,000 if the building is completed by July 31, 2015. The bonus is reduced by $10,000 each week that completion is delayed. Company commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:
| Completed by | Probability |
| July 31, 2015 | 65% |
| August 7, 2015 | 25% |
| August 14, 2015 | 5% |
| August 21, 2015 | 5% |
What is the transaction price for this deal? Show your computations!