Question: Tasks dependent Duration (days) cost A none 1 50 B Starts at the same as A 2 100 C D A (Finish to start relationship)

Tasks dependent Duration (days) cost
A none 1 50
B Starts at the same as A 2 100

C

D

A (Finish to start relationship)

B (Finish to start relationship)

2

2

200

100

Project Progress Report at the end of day 2

Task % completed Actual cost
A 100% 60
B 80% (of entire task) 110
C 20% (of entire task) 30
D not started

why task C only 100?

PV (50+100+100) = 250