Question: Tasks dependent Duration (days) cost A none 1 50 B Starts at the same as A 2 100 C D A (Finish to start relationship)
| Tasks | dependent | Duration (days) | cost |
| A | none | 1 | 50 |
| B | Starts at the same as A | 2 | 100 |
| C D | A (Finish to start relationship) B (Finish to start relationship) | 2 2 | 200 100 |
Project Progress Report at the end of day 2
| Task | % completed | Actual cost |
| A | 100% | 60 |
| B | 80% (of entire task) | 110 |
| C | 20% (of entire task) | 30 |
| D | not started |
why task C only 100?
PV (50+100+100) = 250