Question: Tasks Time (Min) Predecessors A. Position Passenger Bridge 1 B. Deplane Passengers 9 A C. Service Galleys 15 A D. Service Cabin 11 B E.
| Tasks | Time (Min) | Predecessors |
| A. Position Passenger Bridge | 1 |
|
| B. Deplane Passengers | 9 | A |
| C. Service Galleys | 15 | A |
| D. Service Cabin | 11 | B |
| E. Board Passengers | 14 | C,D,H |
| F. Remove Passenger Bridge | 1 | E |
| G. Unload FWD Compartment | 5 |
|
| H. Load FWD Compartment | 7 | K,L,J |
| I. Unload AFT Compartment | 6 |
|
| J. Load AFT Compartment | 9 | I |
| K. Fuel Airplane | 9 | G,M |
| L. Service Vacuum Toilets | 10 | G |
| M. Service Potable Water | 2 |
|
| N. Start Engines | 0 | F |
focus of the process improvement will be for the 1 4 pm shift.
- Airways would like to increase the number of flights processed to 6 aircrafts/shift. How many actual crews will be needed to achieve this target and what will be the time needed for every flight? What is the efficiency of this arrangement?