Question: Tasks X , Y , and Z must be completed in series to complete a project. The three time estimates ( optimistic , most likely,

Tasks X, Y, and Z must be completed in series to complete a project. The three time estimates (optimistic, most likely, and pessimistic) for each task in days are X: 30,45, and 66 days; Y: 24,42, and 60 days; and Z: 26,50, and 68 days. For each task, calculate
the expected time, te
the standard deviation, sigma
What is the standard deviation for the complete project? Enter this number, but enter only the number to one decimal place (do not enter the word 'days').Tasks X, Y, and Z must be completed in series to complete a project. The three time estimates (optimistic, most likely, and pessimistic) for each task in days are X: 30,45, and 66 days; Y: 24,42, and 60 days; and Z: 26,50, and 68 days. For each task, calculate
the expected time, te
the standard deviation, sigma
What is the standard deviation for the complete project? Enter this number, but enter only the number to one decimal place (do not enter the word 'days').

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!