Question: Tasks X , Y , and Z must be completed in series to complete a project. The three time estimates ( optimistic , most likely,
Tasks X Y and Z must be completed in series to complete a project. The three time estimates optimistic most likely, and pessimistic for each task in days are X: and days; Y: and days; and Z: and days. For each task, calculate
the expected time, te
the standard deviation, sigma
What is the standard deviation for the complete project? Enter this number, but enter only the number to one decimal place do not enter the word 'days'Tasks X Y and Z must be completed in series to complete a project. The three time estimates optimistic most likely, and pessimistic for each task in days are X: and days; Y: and days; and Z: and days. For each task, calculate
the expected time, te
the standard deviation, sigma
What is the standard deviation for the complete project? Enter this number, but enter only the number to one decimal place do not enter the word 'days'
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock