Question: PLEASE SOLVE ASAP EVEN IF ITS WITHOUT EXPLANATION Be sure to answer all parts of this question. Tasks D, M, and C must be completed
PLEASE SOLVE ASAP EVEN IF ITS WITHOUT EXPLANATION
Be sure to answer all parts of this question. Tasks D, M, and C must be completed in series to complete a project. The optimistic time, most likely time, and pessimistic time (in weeks) are given in the table below for each Task. a. What is the expected time to complete the project, T0 ? (Round to two decimal place.) b. What is the standard deviation of the expected time to complete the project, T ? (Round to two decimal place.) c. What is the probability of completing the project in 14 weeks? (Round to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts