Question: TB MC Qu . 0 4 - 3 8 C&A Fast Food has four activities... C&A Fast Food has four activities in serving a customer:

TB MC Qu.04-38 C&A Fast Food has four activities...
C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows:
Activity Processing time per customer Wage rate ($ per hour)
Greet customer 2 seconds 5
Take order 30 seconds 5
Process order 60 seconds 15
Deliver order 5 seconds 8
Assume demand is unlimited. If two additional employees are added to the current bottleneck activity, what will be the average labor utilization?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!