Question: TB MC Qu, 4-69 Here are the data for a... Here are the data for a time-cost CPM scheduling model analysis. The time is in

TB MC Qu, 4-69 Here are the data for a... Here
TB MC Qu, 4-69 Here are the data for a... Here are the data for a time-cost CPM scheduling model analysis. The time is in doys and the costs include both direct and indirect costs. If you crash this project to reduce the total time by one day, whot is the total time of the project and total cost? Multiole Chose Totar time 812 days tosal cost is $2,000 Sotal time in 12 days total cost is $2:100 Totat time a t1 days toin costis $1.850 Fotal brie in t3 oays totai cost is 51:000