Question: TB Problem 4 - 1 3 4 ( Algo ) Hayden, Incorporated, produces two products... Hayden, Incorporated, produces two products, Product A and Product B
TB Problem Algo Hayden, Incorporated, produces two products...
Hayden, Incorporated, produces two products, Product A and Product B Hayden uses a traditional volumebased costing system in which direct labor hours are the allocation base. Hayden is considering switching to an ABC system by splitting its manufacturing overhead cost across three activities: Engineering, Manufacturing, and Inspection. The cost of each activity and usage of the cost drivers are as follows:
Activity Pool Driver Cost of Pool Usage by Product A Usage by Product B
Engineering engineering hours $
Manufacturing direct labor hours
Inspection batches
Hayden manufactures units of Product A and units of Product B per month.
Required:
Calculate the predetermined overhead rate under the traditional costing system.
Calculate the activity rate for Engineering.
Calculate the activity rate for Manufacturing.
Calculate the activity rate for Inspection.
Calculate the indirect manufacturing costs assigned to each unit of Product A under the traditional costing system.
Calculate the indirect manufacturing costs assigned to each unit of Product B under the traditional costing system.
Calculate the indirect manufacturing costs assigned to each unit of Product A under the ABC system.
Calculate the indirect manufacturing costs assigned to each unit of Product B under the ABC system.
Which product is undercosted and which is overcosted under the volumebased cost system compared to ABC?
Step by Step Solution
There are 3 Steps involved in it