Question: (TCO A) Tim Construction Co. began operations in 2016. Construction activity for 2016 is shown below. Tim uses the percentage of completion method. Contract Contract

(TCO A) Tim Construction Co. began operations in 2016. Construction activity for 2016 is shown below. Tim uses the percentage of completion method.

Contract Contract Price Billings Through 12/31/16 Collections Through 12/31/16 Costs to 12/31/16 Estimated Costs to Complete
1 $5,200,000 $3,500,000 $2,600,000 $3,000,000 $1,000,000
2 $3,600,000 $1,500,000 $1,000,000 $820,000 $1,880,000
3 $3,300,000 $1,900,000 $1,800,000 $2,250,000 $1,200,000

What amount of Gross Profit should Tim show on the Income Statement of 2016 related to Contract 3?

$0
$150,000 loss
$150,000 profit
None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!