Question: Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination: Activity
Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination:
| Activity | Duration (days) | Immediate Predecessor(s) |
|---|---|---|
| A | 4 | - |
| B | 11 | - |
| C | 8 | - |
| D | 3 | A |
| E | 5 | C |
| F | 8 | B,D,E |
| G | 17 | D,E |
| H | 8 | F |
| I | 5 | G,H |
| J | 17 | I |
What is the overall duration of the project (in days)? days What is the earliest day you could start activity G? (Write the day number in the field below.) What is the earliest day you could finish activity H? What is the latest day you could start activity A? What is the latest day you could finish activity B? What is the slack time for activity C? days What would be the overall duration of the project if activity H were increased by 4days, from 8to 12days? days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts