Question: TEST II NETWORK MODELING TASK ACTIVITY DURATION PREDECESSOR 1 START 0 - 2 A 10 1 3 B 6 1 4 C 13 2 5

TEST II

NETWORK MODELING

TASK ACTIVITY DURATION PREDECESSOR
1 START 0 -
2 A 10 1
3 B 6 1
4 C 13 2
5 D 9 2
6 E 19 3
7 F 20 3
8 G 2 4,5
9 H 4 6,7
10 I 15 8
11 J 16 9
12 K 12 10,11
13 L 9 12
14 M 6 12
15 FINISH 0 13,14

INSTRUCTION

Use Excel to Draw the Network Diagram and compute the following'

Draw the Network Diagram using Excel

Color the Critical Path in RED

TASK ACTIVITY ES EF LS LF SLACK
1 START
2 A
3 B
4 C
5 D
6 E
7 F
8 G
9 H
10 I
11 J
12 K
13 L
14 M
15 FINISH