Question: The CyClon project team has started gathering the information necessary to develop a project network predecessor activities and activity time in days. The results of

The CyClon project team has started gathering the information
necessary to develop a project networkpredecessor activities and
activity time in days. The results of their meeting are found in the
following table.
Activity Description Duration Predecessor
1 CyClon
Project
2 Design 10
3 Procure
prototype
parts
102
4 Fabricate
parts
82
5 Assemble
prototype
43,4
6 Laboratory
test
75
7 Field test 106
8 Adjust
design
67
9 Order stock
components
108
10 Order
custom
components
158
11 Assemble
test
production
unit
109,10
12 Test unit 511
13 Document
results
312
Part A. Create a network based on the information in the table. How
long will the project take? What is the critical path?
Part B. Upon further review the team recognize that they missed three
finish-to-start lags. Procure prototype parts will involve only 2 days of
work but it will take 8 days for the parts to be delivered. Likewise, Order
stock components will take 2 days of work and 8 days for delivery and
Order custom components will take 2 days of work and 13 days for
delivery.
Reconfigure the CyClon schedule by entering the three finish-to-start
lags. What impact did these lags have on the original schedule? On the
amount of work required to complete the project?
Part C. Management is still not happy with the schedule and wants the
project completed as soon as possible. Unfortunately, they are not willing
to approve additional resources. One team member pointed out that the
network contained only finish-to-start relationships and that it might be
possible to reduce project duration by creating start-to-start lags. After
much deliberation the team concluded that the following relationships
could be converted into start-to-start lags:
1. Procure prototype parts could start 6 days after the start of Design.
2. Fabricate parts could start 9 days after the start of Design.
3. Laboratory test could begin 1 day after the start of Assemble prototype.
4. Field test could start 5 days after the start of Laboratory test.
5. Adjust design could begin 7 days after the start of Field test.
6. Order stock and Order custom components could begin 5 days after
Adjust design.
7. Test unit could begin 9 days after the start of Assemble test production
unit.
8. Document results could start 3 days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine start-to-start lags.
What impact did these lags have on the original schedule (Part A)? How
long will the project take? Is there a change in the critical path? Is there a
change in the sensitivity of the network? Why would management like
this solution?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!