Question: The CyClon project team has started gathering the information necessary to develop a project network predecessor activities and activity time in days. The results of
The CyClon project team has started gathering the information
necessary to develop a project networkpredecessor activities and
activity time in days. The results of their meeting are found in the
following table.
Activity Description Duration Predecessor
CyClon
Project
Design
Procure
prototype
parts
Fabricate
parts
Assemble
prototype
Laboratory
test
Field test
Adjust
design
Order stock
components
Order
custom
components
Assemble
test
production
unit
Test unit
Document
results
Part A Create a network based on the information in the table. How
long will the project take? What is the critical path?
Part B Upon further review the team recognize that they missed three
finishtostart lags. Procure prototype parts will involve only days of
work but it will take days for the parts to be delivered. Likewise, Order
stock components will take days of work and days for delivery and
Order custom components will take days of work and days for
delivery.
Reconfigure the CyClon schedule by entering the three finishtostart
lags. What impact did these lags have on the original schedule? On the
amount of work required to complete the project?
Part C Management is still not happy with the schedule and wants the
project completed as soon as possible. Unfortunately, they are not willing
to approve additional resources. One team member pointed out that the
network contained only finishtostart relationships and that it might be
possible to reduce project duration by creating starttostart lags. After
much deliberation the team concluded that the following relationships
could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin day after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days after
Adjust design.
Test unit could begin days after the start of Assemble test production
unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
What impact did these lags have on the original schedule Part A How
long will the project take? Is there a change in the critical path? Is there a
change in the sensitivity of the network? Why would management like
this solution?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock