Question: thank you and can you include the expected duration please. A D G B E H F Activity Time A 6 B C 3 D
thank you and can you include the expected duration please.
A D G B E H F Activity Time A 6 B C 3 D E NA NO F G H J What is the critical path for this project

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock