Question: with the final activity being: Activity: R, predecessor: H, B, F, Duration: 5 Activity C A D G B E H F Predecessor Duration (days)

with the final activity being:
Activity: R, predecessor: H, B, F, Duration: 5
Activity C A D G B E H F Predecessor Duration (days) 6 5 C 3 A 3 D G 7 D 2 G 4 E 7 a) Draw an AOA network diagram. Put activity letters into circles and label the circle with the duration. b) Identify all the path in the network diagram, and their durations. c) What is the critical path of the project? How long is it? d) What is the shortest possible time it will take to complete the projectStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
